Washington State Department of Transportation (WSDOT) will be fixing potholes and repairing the road between the Preston interchange at Southeast 82nd Street and Highlands Drive in Issaquah. Expect long delays and disruption, please plan accordingly. Follow the WSDOT blog for more detailed information. See information on the first set of closures below.
First Set of Closures
April 10-April 12 Closures
- Date/time: April 10 at 10 a.m. through April 12 at 6 p.m.
- Location: WSDOT will reduce a section of westbound I-90 east of Issaquah (between Exit 18 and 20) to one lane around the clock. The construction will be 3.5 miles west of the Preston interchange (see map below).
- Purpose: Fix potholes, repair pavement, replace bridge deck
The lane reduction provides a safe work area for the people repairing I-90. These are a continuation of repairs WSDOT began in summer 2022.
April 16-April 20 Closure
- Date/time: April 16 at 9 p.m. through April 20 at 4 a.m.
- Location: WSDOT will reduce a section of westbound I-90 east of Issaquah (between Exit 18 and 20) to one lane around the clock. The construction will be 3.5 miles west of the Preston interchange (see map below).
- Purpose: Fix potholes, repair pavement, replace bridge deck
The lane reduction provides a safe work area for the people repairing I-90. These are a continuation of repairs WSDOT began in summer 2022.
May 15-17 Closure
- Date/time: May 15 at 10 a.m. through May 17 at 6 p.m.
- Location: WSDOT will reduce a section of westbound I-90 east of Issaquah to one lane around the clock. The construction will be 1 mile west of the Preston interchange (see map below).
- Purpose: Fix potholes, repair pavement, replace bridge deck
The lane reduction provides a safe work area for the people repairing I-90. These are a continuation of repairs WSDOT began in summer 2022.
May 22-24 Closure
- Date/time: May 22 at 10 a.m. through May 24 at 6 p.m.
- Location: WSDOT will reduce a section of westbound I-90 east of Issaquah to one lane around the clock. The construction will be 1 mile west of the Preston interchange (see map below).
- Purpose: Fix potholes, repair pavement, replace bridge deck
The lane reduction provides a safe work area for the people repairing I-90. These are a continuation of repairs WSDOT began in summer 2022.

Second Set of Closures
WSDOT is planning four additional multi-day closures in the same area of I-90 to support bridge deck repairs. These will occur on westbound I-90 about 4 miles west of the Preston interchange, and on eastbound I-90 about a mile east of the interchange. WSDOT has not yet released the dates of these. You can check their blog for more details.